- Confirmation of short list for demonstration of proof of concept for common UC Middleware - 05/14/10 Completed
- Identify candidates for pilot/proof of concept for common UC Middleware - 05/21/10 Completed
- Present candidates to ITLC for provisional approval - 05/27/10 Completed
- Identify Team Members for P1 (architectural design concept) of Pilot - 6/24/10 Completed
- Identify and confirm functional design criteria for User Provisioning - 7/16/10 Completed
- Start Technical Design/Use Case Creation - 7/16/10 Completed
- Hold Working Session for User Provisioning to start concept design - 07/16/10 Completed
- First Draft High Level Design components – 8/3/10 Completed
- Consolidate High Level Design components – 8/17/10 Completed
- Review consolidated Draft High Level Design components with Mary Doyle – 8/17/10 Completed
- Distribute High Level Design to ITAG & UCTrust for validation and input – 8/24/10 Completed
- Incorporate input from ITAG & UCTrust to High Level Design validation and finalize High Level Design – 9/14/10 Completed
- Provide High Level Project Plan for User Provisioning Infrastructure – 9/14/10 Completed
- Identify potential candidates for User Provisioning/Middleware project – 9/14/10 Completed
- Complete Draft Proposal for User Provisioning/UC Wide ITLC Middleware Project for ITLC – 9/21/10 Completed
- Incorporate draft resource and time estimates to Draft High Level Project Plan for Provisioning Infrastructure – 9/21/10 Completed
- Finalize Proposal to present to ITLC 9/28 – 9/22/10 Completed
- Present Proposal for User Provisioning/UC Wide ITLC Middleware Project for ITLC – 9/28/10 Completed
- Complete Phase 1 of Project - 9/30/10 - Completed
- Identify Team for User Provisioning/Detail Design for UC Wide ITLC Middleware Project for ITLC – 11/10/10 Completed
- Hold initial Detail Design Planning Session 11/19/10 Completed
- Start Detail Design for User Provisioning – 1/28/11 Completed
- Create One Page Summary and Architectural Diagram for Detail Design for User Provisioning – 2/7/11 Completed
- Strategize Detail Design Components 2/15/11 Completed
- Identify 2 candidates to prepare Use Cases/Detail Design for: Connexxus and Service Now 2/15/11 Completed
- Reach out to re Shibboleth network at other campuses re federated provisioning - 3/3/11 Completed
- Create Use Case Design Diagram - 3/8/11 Completed
- Create Component Diagram - 3/16/11 Completed
- Meet with key leads in Shibboleth federated network to communicate and confirm design strategy - 3/17/11 Completed
- Create Detail Design Outline – 5/20/11 Completed
- Hold 2 day detail design working session 5/19/11-5/20/11 Completed
- Start Detail Design Documentation – 5/20/11 Completed
- Create Data Release and Governance guidelines – 6/7/11 - Completed
- Update Conceptual Design – 8/9/11 In Progress
- Review Design with staff developers - 8/15/11
- Review Design with ITAG & UCTrust – 8/30/11
- Prepare ITLC presentation - 9/10/11