Milestones and Status

Status as of 08/01/11:

Overall Project Status Notes:

Work on a conceptual design is in progress, and the next checkpoint is scheduled 8/12/11. The conceptual design will be validated with ITAG and UCTrust members once work on it is finalized. The team is also planning on validating the design with key members of their development staff who are unfamiliar with the project as a litmus test.

Milestones/Accomplishments Since Last Report:

• Create Conceptual Design Outline – 5/20/11 Completed
• Hold 2 day working session 5/19/11-5/20/11 Completed
• Start Conceptual Design Documentation – 5/20/11 Completed
• Data Release – Governance – 6/7/11 Completed

Upcoming Milestones/Accomplishments Due Before Next Report:

• Update Conceptual Design – 8/9/11 In Progress
• Review Design with staff developers - 8/15/11
• Review Design with ITAG & UCTrust – 8/30/11
• Prepare ITLC presentation - 9/10/11

Milestones: