# | Task | Predecessors | Duration |
---|---|---|---|
1 | Preparation and Detailed Planning |
|
|
1.1 | Staffing/Recruiting |
| week 1 - week 6 |
1.2 | Develop Detailed Project Plan | 1.1 | week 3 - week 7 |
1.3 | Develop Detailed Architecture | 1.1 | week 3 - week 7 |
2 | Design, Build, and Test |
|
|
2.1 | Technology evaluation and selection (e.g., middleware suite selection) | 1.3 | week 7 - week 13 |
2.2 | Develop Communications Plan | 1.3 | week 7 - week 13 |
2.3 | Design and Implement Common IAM Interface | 2.1 | week 13 - week 40 |
2.4 | Prepare Product Documentation | 2.2, (2.3) | week 36 - week 44 |
2.5 | Test, QA | (2.3) | week 36 - week 44 |
2.6 | Release Product | 2.4, 2.5 | week 45 |
3 | Deployment (done by each UC location) |
|
|
3.1 | Implement Group Management |
| ? - week 64 |
3.2 | Implement eduPersonTargetedID |
| ? - week 64 |
3.3 | If not already done, establish campus policy, procedure, and relationships for brokering requests for identity attributes |
| ? - week 64 |
3.4 | Integrate Common IAM Interface with local IAM (Snapshot) | 2.6, 3.1, 3.2, 3.3 | week 65 - week 80 |
3.5 | Integrate Common IAM Interface with local IAM (Subscription and Change Log) | 2.6, 3.1, 3.2, 3.3 | week 80 - week 100 |