Status as of 06/01/11- Milestones/Accomplishments Completed: - Reach out to re Shibboleth network at other campuses re federated provisioning - 3/3/11 Completed
- Create Use Case Design Diagram - 3/8/11 Completed
- Create Component Diagram - 3/16/11 Completed
- Meet with key leads in Shibboleth federated network to communicate and confirm design strategy - 3/17/11 Completed
- Create Detail Design Outline – 5/20/11 Completed
- Hold 2 day detail design working session 5/19/11-5/20/11 Completed
- Start Detail Design Documentation – 5/20/11 Completed
Milestones/Accomplishments Due: - Document use cases and diagrams – Mukesh 6/3/11 (Lucas will assist)
- Data Release – Governance – Dedra 6/3/11 (David will review/edit)
- Overall editing of the Design page – Dedra 6/10/11
- Internal design review with developers unfamiliar with project to validate completed - Dedra, David, Albert 6/21/11
- Design review with ITAG and UCTrust completed – 6/30/11
- Identify potential pilot projects (can be more than 1) - 6/30/11
- Prepare formal presentation for ITLC - 7/10/11
- Obtain ITLC approval and funding to utilize detail design on pilot project – 7/14/11
More milestones and updates... |