titleMilestones and Status

Status as of 08/01/11 -

Overall Project Status Notes:

Work on a conceptual design is in progress, and the next checkpoint is scheduled 8/12/11. The conceptual design will be validated with ITAG and UCTrust members once work on it is finalized. The team is also planning on validating the design with key members of their development staff who are unfamiliar with the project as a litmus test.

Milestones/Accomplishments Since Last Report:

• Create Conceptual Design Outline – 5/20/11 Completed
• Hold 2 day working session 5/19/11-5/20/11 Completed
• Start Conceptual Design Documentation – 5/20/11 Completed
• Data Release – Governance – 6/7/11 Completed

Upcoming Milestones/Accomplishments Due Before Next Report:

• Update Conceptual Design – 8/9/11 In Progress
• Review Design with staff developers - 8/15/11
• Review Design with ITAG & UCTrust – 8/30/11
• Prepare ITLC presentation - 9/10/11

 
More milestones and updates...

Column
width40%
[UC IDM User Provisioning Middleware: Technical Design Working Draft 03|^draft-ucitag-idmprovisioning-tech-design-03.docx] ?\[docx\03 ?[docx]
  • User Provisioning Design Working Draft 01
  • Related Information:

    Presentations

    Panel
    titleArtifacts

    Current Documents

    Completed Documents

    Archived Documents

    Wiki Markup
    Column
    width20%
    Panel
    titleProject Information

    Archived Work