Status as of 0608/01/11 - Milestones/Accomplishments Completed: Reach out to re Shibboleth network at other campuses re federated provisioning - 3/3/11 CompletedCreate Use Case Design Diagram - 3/8/11 CompletedCreate Component Diagram - 3/16/11 CompletedMeet with key leads in Shibboleth federated network to communicate and confirm design strategy - 3/17/11 CompletedOverall Project Status Notes: Work on a conceptual design is in progress, and the next checkpoint is scheduled 8/12/11. The conceptual design will be validated with ITAG and UCTrust members once work on it is finalized. The team is also planning on validating the design with key members of their development staff who are unfamiliar with the project as a litmus test. Milestones/Accomplishments Since Last Report: • Create Conceptual Create Detail Design Outline – 5/20/11 Completed • Hold 2 day detail design working session 5/19/11-5/20/11 Completed • Start Detail Conceptual Design Documentation – 5/20/11 Completed
Milestones/Accomplishments Due: Document use cases and diagrams – Mukesh 6/3/11 (Lucas will assist) • Data Release – Governance – Dedra 6/ 37/11 (David will review/edit)Overall editing of the Design page – Dedra 6/10/11Internal design review with developers unfamiliar with project to validate completed - Dedra, David, Albert 6/21/11Design review with ITAG and UCTrust completed – 6/30/11Identify potential pilot projects (can be more than 1) - 6/30/11Prepare formal presentation for ITLC - 7/10/11Obtain ITLC approval and funding to utilize detail design on pilot project – 7/14/11Completed
Upcoming Milestones/Accomplishments Due Before Next Report: • Update Conceptual Design – 8/9/11 In Progress • Review Design with staff developers - 8/15/11 • Review Design with ITAG & UCTrust – 8/30/11 • Prepare ITLC presentation - 9/10/11 More milestones and updates... |