User Provisioning Project - ITLC Middleware Project

Note: This is the User Provisioning wiki's old home page. It has been archived. Please refer to the wiki's current home page.

Table of Contents
minLevel2
maxLevel3

...

The goals specific to this project are:  A Pilot/Proof of concept operationalization of common UC Middleware and a White Paper with recommendation for common UC Middleware standards going forward.

User Provisioning has been selected as the proof of concept project for the ITLC Middleware Project.

User Provisioning Proof of Concept Project Overview and Goals:

...

Milestones/Accomplishments Since Last Report;

  • Start Detail Design for User Provisioning – 1/28/11 Completed

 Upcoming Milestones/ Next Steps Due Before Next Report:

  • Create One Page Summary and Architectural Diagram for Detail Design for User Provisioning – 2/4/11 In Progress

 Milestones:

  • Confirmation of short list for demonstration of proof of concept for common UC Middleware - 05/14/10 Completed
  • Identify candidates for pilot/proof of concept for common UC Middleware - 05/21/10 Completed
  • Present candidates to ITLC for provisional approval - 05/27/10 Completed
  • Identify Team Members for P1 (architectural design concept) of Pilot - 6/24/10 Completed
  • Identify and confirm functional design criteria for User Provisioning - 7/16/10 Completed
  • Start Technical Design/Use Case Creation - 7/16/10 Completed
  • Hold  Working Session for User Provisioning to start concept design - 07/16/10 Completed
  • First Draft High Level Design components – 8/3/10 Completed
  • Consolidate High Level Design components – 8/17/10 Completed
  • Review consolidated Draft High Level Design components with Mary Doyle  – 8/17/10 Completed
  • Distribute High Level Design to ITAG & UCTrust for validation and input – 8/24/10 Completed
  • Incorporate input from ITAG & UCTrust to High Level Design validation and finalize High Level Design – 9/14/10 Completed
  • Provide High Level Project Plan for User Provisioning Infrastructure – 9/14/10 Completed
  • Identify potential candidates for User Provisioning/Middleware project – 9/14/10 Completed
  • Complete Draft Proposal for User Provisioning/UC Wide ITLC Middleware Project for ITLC – 9/21/10 Completed
  • Incorporate draft resource and time estimates to Draft High Level Project Plan for Provisioning Infrastructure – 9/21/10 Completed
  • Finalize Proposal to present to ITLC 9/28 – 9/22/10 Completed
  • Present Proposal for User Provisioning/UC Wide ITLC Middleware Project for ITLC – 9/28/10 Completed
  • Complete Phase 1 of Project - 9/30/10 - Completed
  • Identify Team  for User Provisioning/Detail Design for UC Wide ITLC Middleware Project for ITLC – 11/10/10 Completed
  • Hold initial Detail Design Planning Session 11/19/10 Completed
  • Start Detail Design for User Provisioning – 1/28/11 Completed
  • Create One Page Summary and Architectural Diagram for Detail Design for User Provisioning – 2/4/11 In Progress
  • Develop approach and plan to implement a demonstration of the proof of concept project – 3/15/11
  • Estimate Resources required at each campus and UC-wide approach – 3/15/11
  • Complete Detail Design – 4/15/11 In Progress
  • Implement Proof of Concept Project - 12/31/11

...