titleMilestones and Status

Status as of 06/01/11-

Milestones/Accomplishments Completed:

  • Reach out to re Shibboleth network at other campuses re federated provisioning -  3/3/11 Completed
  • Create Use Case Design Diagram - 3/8/11 Completed
  • Create Component Diagram - 3/16/11 Completed
  • Meet with key leads in Shibboleth federated network to communicate and confirm design strategy - 3/17/11 Completed
  • Create Detail Design Outline – 5/20/11 Completed
  • Hold 2 day detail design working session 5/19/11-5/20/11 Completed
  • Start Detail Design Documentation – 5/20/11 Completed

Milestones/Accomplishments Due:

  • Document use cases and diagrams – Mukesh 6/3/11 (Lucas will assist)
  • Data Release – Governance – Dedra 6/3/11 (David will review/edit)
  • Overall editing of the Design page – Dedra 6/10/11
  • Internal design review with developers unfamiliar with project to validate completed - Dedra, David, Albert 6/21/11
  • Design review with ITAG and UCTrust completed – 6/30/11
  • Identify potential pilot projects (can be more than 1) - 6/30/11
  • Prepare formal presentation for ITLC - 7/10/11
  • Obtain ITLC approval and funding to utilize detail design on pilot project – 7/14/11

 
More milestones and updates...

Column
width40%
Panel
titleArtifacts

Current Documents

Completed Documents

Outdated Drafts

Related Information:

Presentations

Column
width20%
Panel
titleProject Information

Archived Work